Loading ...

[Newnham Campus] Road and parking lot repairs scheduled for week of Aug. 18 | MyNews | Seneca Students

Home » Spaces » MyNews » Articles » [Newnham Campus] Road and parking lot repairs scheduled for week of Aug. 18
MyNews

Leave Space :

Are you sure you want to leave this space?

Join this space:

Join this space?

Edit navigation item

Required The name that will appear in the space navigation.
Required
Required
Required The url can point to an internal or external web page.
 
Login to follow, share, and participate in this space.
Not a member?Join now
Version 1
[Newnham Campus] Road and parking lot repairs scheduled for week of Aug. 18

[Newnham Campus] Road and parking lot repairs scheduled for week of Aug. 18

 /5
0 (0votes)

Repair and maintenance work for select roadways and parking lots at Newnham Campus have been scheduled for the week of Monday, Aug. 18.

While signage and barriers will be put up for the safety of our students, employees, visitors and the external community, please review the following sections so that you know what to expect and can plan ahead if needed.

 Au Large Blvd. and Premier Davis Blvd.  | Roadway pavement repair

  • Evening and overnight lane closures of the campus roadways on Tuesday, Aug. 19 and Wednesday, Aug. 20, starting at 7 p.m. until 7 a.m. the next day, respectively
  • Completion by the morning of Thursday, Aug. 21
  • Vehicle traffic will be permitted for the duration of the repair, as no complete closure of all lanes will be scheduled at any time

 Lot 1  | Asphalt patching

  • Lot to close evening of Monday, Aug. 18 and reopen on Wednesday, Aug. 20

 Lot 4  | Line painting

  • Lot to close on Thursday, Aug. 21 and reopen on Friday, Aug. 22